Excavation is where your custom pool design becomes physical reality. It's also where the most unexpected things typically happen.
Excavation is where your custom pool design becomes physical reality. It's also where the most unexpected things typically happen.
This guide walks through the excavation process, what you'll see happening on-site, what can go wrong, and how to prepare for it.
The Excavation Overview
Duration: 2–6 weeks (simple to complex sites)
Team: Heavy equipment operators, excavators, grading equipment, spotters
Key equipment: Backhoes, excavators, dozers, dump trucks, compactors, water pumps
Purpose: Dig the basin to exact depth and dimensions, grade surrounding area for water management and decking
Step-by-Step: What Actually Happens
Step 1: Layout and Marking (Days 1–2)
Before any equipment moves, the pool footprint is marked precisely:
- Surveyors or builder marks exact pool perimeter with stakes/chalk
- Equipment operator reviews plans
- Any underground utilities are located and marked (critical safety step)
- Temporary fencing or warnings placed
Why this matters: Getting the footprint wrong costs thousands to correct later.
Step 2: Remove Top Layer / Topsoil Stripping (Days 2–3)
- Remove topsoil and vegetation from pool area (12–18 inches deep)
- Separate good soil (can be reused for landscaping) from poor soil (haul away)
- This exposes subsoil where actual pool excavation will happen
Why this matters: Topsoil is unsuitable for pool basin. Must reach stable subsoil before excavating pool depth.
Step 3: Excavate Pool Basin (Days 3–14, depending on conditions)
This is the main excavation. The backhoe or excavator removes soil to the designed pool depth.
Standard procedure: - Operator digs in layers (typically 2–3 feet per pass) - Soil is loaded into dump trucks - Trucks haul soil off-site (or stockpile for later grading) - Operator continuously checks depth with surveying equipment
Timeline depends on: - Pool size (larger pool = more volume to remove) - Soil type (clay is harder than sandy soil) - Rock/hardpan (may require additional equipment or blasting) - Equipment access
What you'll see: - Heavy equipment operating continuously - Trucks coming and going - Dust and noise - Operator checking plans constantly
Step 4: Check Grade and Slope (Days 14–21)
Once excavation reaches target depth, the builder:
- Surveys the bottom to ensure correct depth everywhere
- Checks slope (if pool has beach entry or sloped floor)
- Identifies any low spots that need adjustment
Why this matters: Pool floor must be level (or correctly sloped if intentional). Any low spots will be uneven water depth.
Step 5: Final Grade and Drainage Preparation (Days 21–25)
- Final adjustments to basin floor
- If drainage engineering is required, drainage lines are installed
- Surrounding area is graded to direct water away from pool
Why this matters: Poor drainage around pool causes long-term foundation issues. Proper grading prevents water from collecting near pool edge.
Step 6: Compact Soil (Day 25–26)
- Pool basin floor is compacted (vibrating compactor) to make it stable
- This prevents settling after pool is built
Why this matters: Uncompacted soil settles, causing pool basin to shift over time. Compaction prevents this.
What Can Go Wrong During Excavation
Discovery: Rock or Hardpan
What it is: Layer of solid rock or compressed soil (hardpan) beneath topsoil.
Why it matters: Standard excavation equipment can't penetrate rock. Requires: - Specialized equipment (jackhammer attachments) - Or blasting - Or hand excavation
Cost impact: +$3,000–$15,000 (depending on how much rock)
Timeline impact: +2–4 weeks
How to prevent: Geotechnical assessment can identify rock before excavation. Worth $800–$1,500 to avoid surprise cost.
Discovery: Groundwater
What it is: Water table higher than expected, causing water to seep into excavation.
Why it matters: Can't build pool foundation in water-filled pit. Requires: - Dewatering (pumping water out continuously) - Possibly adjusting pool depth - Additional drainage engineering
Cost impact: +$2,000–$8,000
Timeline impact: +1–2 weeks
How to prevent: Geotechnical assessment. Seasonal assessment (wet season vs. dry) matters. Neighbor information about water issues.
Discovery: Utility Lines
What it is: Water, electrical, gas, or telecom lines in excavation path.
Why it matters: Hitting utilities: - Damages service (utility company charges repair) - Safety hazard - Halts excavation while utility company locates/marks - Can cost $5,000–$20,000 in damages + delays
How to prevent: Call 811 (Dig Safe) before excavation. Utility companies mark lines. Still require spotters to verify during digging.
Challenge: Difficult Site Access
What it is: Equipment can't reach certain areas due to terrain, gates, trees, or neighbors' properties.
Why it matters: May require: - Hand excavation (people with shovels instead of equipment) - Smaller equipment - Additional access agreements with neighbors - More time and labor
Cost impact: +$3,000–$15,000 depending on severity
Timeline impact: +2–6 weeks
The Logistics of Excavation
Where Does All the Soil Go?
Typically: - Good fill soil: Stockpiled on-site for use in grading/landscaping (saves cost) - Poor quality soil: Hauled to disposal site (costs $30–$60/load) - Typical pool: Removes 100–200 tons of soil (requires 15–40 truck loads)
Cost: $1,500–$3,500 for haul-away (often included in site work quote)
Equipment Parking and Access
- Excavation equipment parks on-site or nearby
- Trucks need clear access routes
- Neighbors may be impacted by truck traffic
Preparation: - Discuss with neighbors before excavation - Establish hours (typically no weekend/evening work) - Plan traffic routes to minimize impact
Noise and Dust
- Heavy equipment generates 85–95 dB noise (very loud)
- Excavation creates dust
- Both typically occur during business hours (7 AM – 5 PM)
Mitigation: - Dust suppressant can be sprayed - Schedule around neighbor considerations where possible
What You Should Monitor During Excavation
Week 1
- Is footprint marked correctly? (Compare to plans)
- Are utility markings visible? (Can see 811 paint marks)
- Is excavation equipment appropriate for site?
Week 2
- Is depth correct? (Should see surveying checks)
- Is quality of fill soil good? (Rocks/clay vs. sandy soil)
- Any rock or water discovered?
Week 3–4
- Is floor level being maintained?
- Is drainage grading correct?
- Any surprises emerging?
Don't be shy about asking questions. Your builder should explain what's happening and address concerns.
Frequently Asked Questions
How much soil does a typical pool excavation remove?
For a 20×40 ft pool at 5 ft deep: Approximately 150–170 tons of soil. That's 15–20 truck loads.
What does geotechnical assessment actually cost and is it worth it?
Cost: $800–$1,500
Worth it? Absolutely if your site is unknown or has history of problems. Prevents $5,000–$15,000 in surprises during excavation.
Can I keep the excavated soil for landscaping later?
Yes, if it's good quality. Sandy or clay soil can be reused. Topsoil should definitely be kept. Stockpile on-site during construction.
How long until I can see the pool basin taking shape?
2–3 weeks into excavation. Once topsoil is removed and basin is dug, you can see the footprint clearly. Exciting milestone.
Have questions about planning, building, or improving your custom pool? Scott Payne Custom Pools serves PA and NJ with straight answers and no pressure.
Get a Free Consultation